Boeing yesterday shuffled the line-up of the 787s on the final assembly line in
The 787 designated for fatigue testing was moved out of the final assembly factory to another production bay, which was not disclosed. The fatigue test airplane is not yet complete and assembly work will continue in the new location.
The move allows the second flight test aircraft to advance one position on the four-stage assembly line. Meanwhile, the third flight test aircraft will remain in the first position until assembly is ready to start on the fourth flight test.
©Boeing
Vought Aircraft has already shipped the aft fuselage sections for the fourth flight test aircraft, and shipments from Spirit AeroSystems of the nose section and from Global Aeronautica of the centre fuselage were scheduled to arrive in
The first flight test aircraft remains in the nose-to-door position on the assembly line.
Boeing completed the one-week sequence of power-on tests for the first flight test aircraft on 19 June. First flight is scheduled in the fourth quarter this year.
Click here to subscribe to Flightglobal.com for more industry news and analysis.
FlightBlogger Exclusive: Boeing delays Dreamliner Four in Charleston after structural damage
(01/07/08)
Boeing completes 787 power-on testing
(20/06/08)
Monarch faces 30-month delay on 787s
(20/06/08)
Flightglobal is offering a series of FREE ‘What Works Online’ webinars to equip you with the knowledge, resources and best practice advice to help you achieve your business goals
Learn how to reach new customers through online advertising and email marketing, drive traffic through SEO and generate new leads online
Don’t miss this free training opportunity delivered by experts in online marketing