On-going replacement of thousands of Boeing 787 fasteners has frozen the production line, as the airframer conducts a formal assessment of the programme's schedule, including the timeline for first flight and delivery.
Significant programme resources have been brought to bear as work continues on replacing fasteners and providing flight-test aircraft with a clean structural bill of health.
Boeing declines to comment on the pace of the on-going schedule assessment.
But ATI affiliate Flightblogger reports that, according to sources familiar with the fastener replacement timeline, the expected completion of the fix for Dreamliner One should come by the end of December.
The effects of the fastener replacement, however, are reverberating down the 787 assembly line. Sources at Everett state that no production airframe movements are scheduled for the remainder of the year, resulting in final assembly start for Dreamliner Five - the first General Electric GEnx-powered 787 - being pushed into 2009.
For more articles like this in real time, take a free trial to Air Transport Intelligence (ATI).
FAA clears 787 maintenance programme
(22/12/08)
Delta uncertain over 787 order
(10/12/08)
Delta uncertain over 787 order
(09/12/08)
Learn how to reach new customers through online advertising and email marketing, drive traffic through SEO and generate new leads online with Flightglobal's 'What Works Online' webinar series
Don’t miss you opportunity to be trained by the experts
Flightglobal is offering a series of FREE ‘What Works Online’ webinars to equip you with the knowledge, resources and best practice advice to help you achieve your business goals
Learn how to reach new customers through online advertising and email marketing, drive traffic through SEO and generate new leads online
Don’t miss this free training opportunity delivered by experts in online marketing