Ares V timeline
  • Ares V request for proposals 5 January 2009
  • Concept review 21 April 2009
  • Phase one contracts awarded Q2 2009
  • Functional feasibility review 25 August 2009
  • Preliminary requirements review 23 March 2010
  • Concept design review December 2010
  • Level two system requirement review 2010
  • Level three system requirement review 2011
  • Authority to proceed 2011
  • Level three system definition review 2012
  • Phase two DDT&E and production contracts March 2012
  • Ares V elements' preliminary design review Q3 2013 to Q1 2014
  • Ares V elements' critical design review 2016
  • Ares V test flight 2018, first lunar mission December 2019

Rate this article
12345
Poor   Outstanding
Average rating: 3 out of 5

Click here to check out the highest rated articles
 

On AirSpace now

gate64

....and 574 guest(s)

Join us

For exclusive news and expert analysis every week subscribe to Flight International print edition. Included with your subscription are 4 FREE issues and FREE delivery to your home or office.