FlightBlogger: 787's path to first flight detailed

Boeing's 787 Dreamliner program has had five first flight dates set, but a timeline for key program milestones has now emerged that outlines a grueling testing gauntlet to first flight in late April, sources tell FlightBlogger.

Starting late on 2 January, Dreamliner One will depart its home in Building 40-26 and make the short trip to an open slot on the 767 line in Building 40-24. ZA001 will occupy the spot currently held by ZY998, the fatigue airframe, which will be moved to the flight line prior to the start of fatigue testing.

Dreamliner One will undergo three gauntlet test phases that will eventually culminate in first flight by late April – nearly two years after the first sections for ZA001 arrived at the Everett factory.

To read the full update, read FlightBlogger’s latest entry here.

Links posted in this story:


Rate this article
12345
Poor   Outstanding
Average rating: 2 out of 5

Click here to check out the highest rated articles
 

Click here to subscribe to Flightglobal.com for more industry news and analysis.


FREE Online Marketing Training

Learn how to reach new customers through online advertising and email marketing, drive traffic through SEO and generate new leads online with Flightglobal's 'What Works Online' webinar series

Don’t miss you opportunity to be trained by the experts

Make the most of the web

Flightglobal is offering a series of FREE ‘What Works Online’ webinars to equip you with the knowledge, resources and best practice advice to help you achieve your business goals

Learn how to reach new customers through online advertising and email marketing, drive traffic through SEO and generate new leads online

Don’t miss this free training opportunity delivered by experts in online marketing