Aircraft

DATE:13/10/09
SOURCE:Flight International
Dreamliner troubles return to haunt 747-8F

The diversion of engineering resources to Boeing's troubled Dreamliner has forced the airframer to give up on its plan to fly the first 747-8 Freighter on 9 December and deliver an aircraft to Cargolux in the third quarter of next year.

The three-month delivery delay, to the fourth quarter of 2010, is being attributed to an accumulation of small engineering issues. One programme engineer likened the delay to "death by 1,000 cuts".

The latest delay forced Boeing to take a third quarter earning charge of $640 million owing to "re-work and disruption" and a further $360 million to cover the cargo market collapse that has forced a scaled-back ramp-up to two aircraft amonth.

With 747-8F resources constrained to feed the 787's demands, "more engineering errors escaped than what could be considered normal", he says, adding that "workers are adjusting to building a new airplane. A lot of them have been moved around...so their work lacks continuity, which leads to production errors."

Of the total number of tasks required to take a 747-8 from structural build to pre-flight activities, just over 50% had been fully completed at the time the delay was announced, according to company sources. Many of the tasks are unfinished owing to engineering changes.

Before the delay announcement, the first 747-8F (RC501) was set to leave the final assembly line for the paint hangar around 11 October.

In May, 747 vice-president and general manager Mohammad "Mo" Yahyavi declared: "I have all the resources I need now for both the freighter and the Intercontinental."

However, the June discovery that the 787's wing-to-body join needed re-engineering left 747-8I launch customer Lufthansa, whose passenger variant service entry remains unchanged, expecting a further programme delay.

Chief financial officer Stephan Gemkow said at the time: "I'm sure again the delay of the 787 will mean that they have to pull in more engineering resources, and that will have even further delays, as a consequence, for the 747-8. I would not be surprised to learn this some weeks or months in the future."

Links posted in this story:


Rate this article
12345
Poor   Outstanding
Average rating: 4 out of 5

Click here to check out the highest rated articles
 

For exclusive news and expert analysis every week subscribe to Flight International print edition. Included with your subscription are 4 FREE issues and FREE delivery to your home or office.


FREE Online Marketing Training

Learn how to reach new customers through online advertising and email marketing, drive traffic through SEO and generate new leads online with Flightglobal's 'What Works Online' webinar series

Don’t miss you opportunity to be trained by the experts

Make the most of the web

Flightglobal is offering a series of FREE ‘What Works Online’ webinars to equip you with the knowledge, resources and best practice advice to help you achieve your business goals

Learn how to reach new customers through online advertising and email marketing, drive traffic through SEO and generate new leads online

Don’t miss this free training opportunity delivered by experts in online marketing