DATE:14/11/08
SOURCE:Air Transport Intelligence news
Boeing delays 777F up to 3 months, blames strike

Boeing today announced that a two-month strike by machinists will delay the 777 Freighter's first delivery to Air France by at least one to three months.

Two 777Fs are expected to complete flight tests on time in December, a Boeing spokeswoman says.

But launch customer Air France will not receive a third 777F currently in final assembly until some time in the first quarter, she adds.

The announcement came on the same day that Boeing delayed the 747-8F by six to nine months and the 747-8 Intercontinental passenger version by four to six months.

However, Boeing emphasizes that the 777F schedule was impacted solely by recently completed, two-month strike by the International Association of Machinists and Aerospace Workers.

By contrast, Boeing also blamed the 747 programme delays on design and supply chain problems, including a "dramatic" enhancement of the 747-8's new wing.

Links posted in this story:

For more articles like this in real time, take a free trial to Air Transport Intelligence (ATI).


FREE Online Marketing Training

Learn how to reach new customers through online advertising and email marketing, drive traffic through SEO and generate new leads online with Flightglobal's 'What Works Online' webinar series

Don’t miss you opportunity to be trained by the experts

Make the most of the web

Flightglobal is offering a series of FREE ‘What Works Online’ webinars to equip you with the knowledge, resources and best practice advice to help you achieve your business goals

Learn how to reach new customers through online advertising and email marketing, drive traffic through SEO and generate new leads online

Don’t miss this free training opportunity delivered by experts in online marketing

 
 
Advanced Search