Orion's heat shield: it's decision time

Rob Coppinger
 on March 6, 2009 3:18 PM | | Comments (5)
|
Thumbnail image for Orion in orbit.jpg
credit Lockheed Martin / caption: the heat shield has become a very tall tent pole in the Orion tent, so to speak

In the next few weeks NASA is to announce its selection for the heat shield material for the Orion crew exploration vehicle's (CEV) crew module. The space agency has told Hyperbola that assuming "all materials and work is completed" the press release could be published this month, so maybe it will actually be April but either way it is a decision that is at least 14-months late

Way back in 2006, before Lockheed Martin Space Systems became Orion prime contractor, it was touting Phenolic Impregnated Carbon Ablator (PICA) as the thermal protection system (TPS) solution citing its use with the Stardust mission that Lockheed built the return capsule for

By December 2006 Lockheed had agreed with NASA that the heat shield would be segmented and not monollithic, a decision that would change, and that it would also use Lockheed's TPS choice, the Stardust mission's PICA, another decision that would also change in the year's to come

However the heat shield was always separate to the main Orion CEV design, development, test and evaluation contract that Lockheed won and in September 2006 Boeing was awarded a contract to examine PICA

But NASA Ames Research Center was leading the work and in that September it was also looking at a super lightweight ablative for what was then termed the Block 1 International Space Station variant crew exploration vehicle

In April 2007 mass issues for Orion were becoming public and the thermal protection system was identified as one of the subsystems being targeted for mass savings 

In May 2007 Boeing got $10 million to look at its own PICA variant for Orion and as well as that NASA started an entirely new "advanced technology development" project and paid Textron Systems $24 million to look at the Apollo Avcoat TPS as a potential backup technology - although due to changes in environmental legislation since the 1960s the Orion Avocat would have to be a "reformulation"

In due course, in November 2007, Boeing delivered a protoytpe PICA heat shield to NASA and by February 2008 the space agency was expecting a preliminary design review (PDR) for its PICA heat shield in April that could have then seen this "subsystem" handed over to Lockheed for "integration" with the rest of the CEV

But this PDR doesn't appear to have come to pass as other considerations for the performance of the heat shield presented major problems for Orion; including its mass margin with a threat of a 20% TPS mass increase required for it to cope safely with lunar return

And then by September last year it was known that the new formulation for Avcoat was edging out PICA in the mass optimisation stakes and that a down select decision, delayed from January 2008, could have been taken during technical discussions in the November that had originally been planned to be the Orion CEV PDR, by then known to be delayed to 2009

During that September however it became clear that the new date for Orion heat shield approval was "early next year" and now we are, where we are

The likely selection of the new Avcoat will not end things though. Two major outstanding Orion mass issues of the TPS and the airbag landing system have been impacting on the launch abort system that in return impacts on the Ares I

It maybe that the TPS selection signals that the airbag conundrum has also been solved and that Orion is finally close to closing on mass and power but this significant technical milestone is not necessarily the beginning of the design reviews' end

Go here for a video of a presentation by Lockheed Martin Orion team members who explain some of the reasons behind the 10-month Orion PDR delay 

5 Comments

Kris Ringwood

Well, well, well,
more proof they had it right to begin with! As with the J-2X engine which has only 26% better performance but weighs almost 225% more than the final J-2 engine of Apollo-Saturn, we find that current "solutions" have drifted so far away from basics, they're on the point of being untenable. It took them 10 months to determine that AVCOAT is superior to PICS??!! By that I mean same performance-less weight. The latter being the Rocket Engineers' Arch Enemy. Good thing this lot weren't doing the original Apollo-Saturn isn't it? We'd never have made the original deadline and been in the middle of re-design #... What a bunch of boondogglers!

E_Moelzer

Ok, so making an ablative(!) heatshield is such a big issue?
Heck this should be about the most low tech part of the whole vehicle. If I am not mistaken the Chinese use simple oakwood? Now if we were talking about a resuable heatshield, that would be a different matter of course but ablative should be straight foreward.
Once again NASA is throwing out money with both hands!

Gab Kamp

Kris/Robbie; how come the J2X is 225% heavier than J2? I didn't hear that till now. A major justification was the original super thrust/weight ratio!

Also I have read that PICA performed superlatively on Stardust and covers LEO, Lunar return and even Mars return. Better in one piece though.

How come Boeing can make it in one piece and LM can't?

Why can't these people give facts instead of leaving everyone guessing? Do they have something to hide?

Does AVCOAT do moon/mars as well?

MT Rob Coppinger

You beat me to it Gab, I was going to ask Kris the same thing, where did he get that 225% heavier figure from? Unless there is some mass figure I have given in the past and forgotten about. Kris - if you don't want to name your source on this blog comment thing then do email me your inside info source on rob.coppinger@flightglobal.com

BTW Gab, Boeing actually provided the PICA heat shield prototype as a segmented system and Avcoat did Moon for Apollo so yes it does that well

Anonymous

The Avcoat 5026-39 wins hands down > a monolithic heatshield > unbeatable ablation effeciency only took 39 heat of ablation tests to field a superior product in 1962 they (avco) got it right c,hemisty has not changed a furnace insulation diped in resin has no legs and tiles are parasitic to the airframe ..congratulations Textron !!

Leave a comment

Want a user picture? Get a Gravatar!

Like Flightglobal on Facebook