P&W pushes back detail design start on geared turbofan

Toulouse
Source:
This story is sourced from Pro
See more Pro news »

Pratt & Whitney has extended the preliminary design phase of its PW1000G geared turbofan for the Bombardier CSeries and Mitsubishi MRJ to mid-2009, to give it more time to work with the airframers before committing to detailed design.

Bombardier completed its key supplier selection for the CSeries in the third quarter of last year and P&W has been engaging in workshops with the chosen parties in preparation for the start of detail design. However with both the CSeries and the MRJ having struggled to secure additional customers, more time is being allowed to define the airframe programmes before starting detail design of the engine.

"We initially had provisioned to start detail design on the engines as early as the beginning of this year, but we now plan to start around mid-2009," says P&W vice-president for the next generation product family Bob Saia.

"In the preliminary design phase we still have the ability to adjust the engine architecture as a function of airframe requirements. By mid-August we'll have all of the detailed requirements frozen from an engine perspective for both airframes. Then we'll go into our detail design phase."

He adds: "We want to ensure we don't have to go back and do any redesign. So we decided to use up some of the margin we had which still allows us to meet the timetable."

Bombardier's slow progress in completing order negotiations with CSeries customers since the programme's launch in July last year, and the similarly sluggish sales of Mitsubishi's MRJ, have not dampened P&W's geared-turbofan development plan, says Saia.

"Customers are going come - they're close to firming up [the orders]," he says. We're confident the programmes are going to go. P&W has over 1,000 engineers doing engineering work on their requirements."

The PW1000G is initially being developed with two fan diameters to match the thrust requirements of the MRJ and CSeries: the 17,000lb-thrust (76kN) PW1217G and 24,000lb-thrust PW1524G respectively. The first engine will begin testing in mid-2010 with certification due in late 2011.

Saia says the MRJ is due to fly in late 2011, followed by the CSeries in early 2012, and that service entry for both airframes and engines is scheduled for the end of 2013.